PMP Exam Beta: Solved by two independent checkers, not yet audited by a person People Read the question and choose the one best answer. A predictive project to replace a hospital's scheduling system has 60 identified stakeholders, and the project manager has limited time for stakeholder work. What should the project manager do first? 1 Interview the department heads to learn what their staff expect of the new system 2 Send all stakeholders the same weekly update while an engagement plan is drawn up 3 Meet the stakeholders who have raised objections so far to understand their concerns 4 Classify the stakeholders by their influence and interest in the project's outcome Report a problem Report this question Tell us what looks wrong with this question. Your report is kept on this device until it can be sent. What is wrong? The answer key is wrong The question is unclear or has more than one answer A typo or display problem The explanation or translation is wrong Something else Details (optional) Up to 500 characters.